Consider what happened on this continent in a single eight-month stretch.
In November 2025, Rio Tinto placed Jadar — a US$2.95 billion lithium-borates project that the European Commission had designated a Strategic Project barely five months earlier — on care and maintenance, citing a lack of permitting progress. In May 2026, Vulcan Energy reached financial close on a roughly €2.2 billion package for its Lionheart geothermal lithium project in Germany, the most complete example yet of European industrial policy expressed as a capital structure. That same month, Sibanye-Stillwater declared construction of the Keliber chain substantially complete, after having already elected a staged start-up that deferred the Kokkola refinery ramp-up decision pending lithium prices. In June, Sweden granted Norra Kärr a 25-year mining lease after a decade in permitting purgatory; a Portuguese court temporarily halted fieldwork at Barroso, until a reasoned government resolution declaring the project of national and European interest removed the order's suspensive effect; and Eldorado Gold reported Skouries 94% complete, with first concentrate expected in the third quarter of 2026.
One continent. One policy framework. Six entirely different outcomes.
Brussels and a growing number of national governments no longer need to be persuaded that Europe requires greater domestic mineral production. They have written that conviction into law, begun funding it and, after successive supply shocks, treated it as a matter of economic security. The harder question has moved: not whether Europe supports mining in the abstract, but whether its institutions can convert support into operating mines faster than courts, markets and communities can interrupt the conversion. What follows is an attempt to answer that question the way a transaction lawyer should: by instrument, by project and by binding constraint.
The policy architecture is real — and the audit is sobering
The Critical Raw Materials Act, in force since May 2024, set the now-familiar 2030 benchmarks: EU capacity to extract at least 10% of annual consumption of strategic raw materials, process at least 40%, recycle at least 25%, and source no more than 65% of any strategic raw material at a relevant processing stage from a single third country. The Commission approved 47 Strategic Projects inside the Union in March 2025 and 13 projects outside the Union in June 2025. A second call closed in January 2026, with further designations expected later in the year.
Around the Act, Brussels has begun constructing a more muscular apparatus: the RESourceEU action plan announced in December 2025, a proposed European Critical Raw Materials Centre, joint-purchasing and offtake-matching tools, coordinated stockpiling and a larger role for the European Investment Bank. These are material developments. They should nevertheless be distinguished by legal status: some are operating programmes, some are funding commitments and some remain implementation plans.
In February 2026, the European Court of Auditors published a broader audit of the raw-material supply required for the energy transition. Its conclusion was blunt: on the present trajectory, the Union's 2030 objectives are out of reach. Domestic extraction, refining and recycling remain underdeveloped, diversification has produced limited tangible results, and even a discovered EU deposit can take many years to reach operation. Separate project-level evidence points in the same direction. In the auditors' sample of nineteen successful applications, only three mature projects were already at the construction stage, and none was in the operational phase. Many were unlikely to contribute before 2030, financing visibility remained uneven and seven lacked a secured or internally integrated offtake.
None of this means the policy has failed. It means the policy has succeeded at the things legislation can do most readily — designation, coordination, priority and public capital — and is now colliding with the things legislation cannot do by itself. Those things are the subject of this article.
What Strategic Project status actually is: a presumption, not an exemption
Much of the commentary on the CRMA treats Strategic Project status as a kind of super-permit. It is worth being precise about what the Regulation actually does, because the gap between the political label and the legal instrument is where projects — and investments — go wrong.
Article 10(2) provides that Strategic Projects are to be considered of public interest for specified derogation regimes under the Habitats, Water Framework and Birds Directives and may be considered to have an overriding public interest where the conditions of those instruments are fulfilled. The word "may" and the final proviso are load-bearing. The appropriate assessment under Article 6(3) of the Habitats Directive must still satisfy the Waddenzee standard: consent only where no reasonable scientific doubt remains as to the absence of adverse effects on the integrity of the protected site.
If the assessment is negative, the Article 6(4) route still requires the absence of alternative solutions and compensatory measures sufficient to protect the overall coherence of Natura 2000. Where priority habitats or species are affected, further constraints may apply. The CRMA therefore materially strengthens a Strategic Project on the public-interest limb of the test for imperative reasons of overriding public interest, or IROPI; it does not complete the analysis. I have not identified a major EU metal mine that has yet reached operation through the full IROPI route. The first clear case would be an important European test.
The permitting clocks deserve the same precision. Article 11 generally caps the permit-granting process at 27 months for extraction and 15 months for processing or recycling; shorter remaining periods apply to projects already in the permitting process when designated. But time spent by the developer preparing the environmental impact assessment report is excluded, requests for supplemental information can affect the clock, and the Regulation imposes no fixed deadline on judicial review. It asks Member States to provide urgent handling only where national law already permits it. The Aarhus framework and EU case law also require meaningful access to judicial review of environmental decisions and significantly constrain attempts to exclude qualified environmental organisations.
Five questions that should replace "shovel-ready"
When a European project is described to me as shovel-ready, I ask five questions.
- Is there a complete permit map — every consent, responsible authority, completeness determination, appeal window and litigation exposure?
- Is the project technically frozen, or will design changes following financing reopen consents already granted?
- Is the financing matched to the actual project — contingency, working capital, ramp-up and downside commodity pricing included?
- Is there a proven route to market — processing capacity, product qualification and customers with acceptance obligations?
- Is the project politically durable — through elections, litigation and a price cycle, in the municipality and not merely in the capital?
A project that clears all five may be capable of conventional project financing whether or not it appears on a Brussels list. A project that materially fails two of them is not yet project-finance-ready, no matter how many lists it appears on. These five questions are also, not coincidentally, the audit we run before a client signs a term sheet.
Eight projects, eight binding constraints
European mining projects are better classified by their binding constraint than by their official status. Some need permits. Some need a viable commodity price. Some need a legally defensible route through environmental law. Some need public trust. The 2025–26 record now lets us watch each constraint operate in real time.
The ledger at a glance: of the eight projects below, three have reached construction or financial close, none has reached full-project commercial production, and the binding constraint differs in almost every case. That distribution — not any single project's fate — is the finding.
| Project | Stage | Public Support / Alignment | Binding Constraint | Next Decisive Milestone |
|---|---|---|---|---|
| Skouries | 94% complete; first concentrate expected Q3 2026 | Revised Greek investment agreement; fully funded construction plan | Commissioning and ramp-up | First concentrate and stable commercial production |
| Keliber | Mine and concentrator start-up commenced; refinery ramp-up deferred | Finnish Minerals Group participation; public and policy finance | Lithium price and full-chain economics | Decision on full Kokkola refinery ramp-up |
| Sakatti | Regional planning and Natura 2000 derogation route; pre-feasibility work ahead | EU Strategic Project status; Finnish planning support | Habitats-law derogation and judicial durability | Government Natura decision and feasibility study |
| Lionheart | Financial close achieved; construction phase | EIB, export-credit support, German grants, policy and industrial equity | Construction, technology and reservoir performance | Delivery to planned 2028 production |
| EMILI | Concession/public-inquiry and demonstration pathway | Major national-interest status; French state minority equity | Full-scale permits, engineering and financing | Concession decision and bankable investment package |
| Cínovec | DFS complete; EIA filed; commissioning indicated around 2031 | ČEZ control; approved state aid of up to €360 million | Remaining approvals and US$2.16 billion capital requirement | EIA/permit decisions and financing plan |
| Barroso | Conditional environmental approval; FID targeted after remaining work | EU status; Portuguese grant of up to €110 million | Land access, social licence and continuing litigation | Durable land-access solution and remaining permits |
| Jadar | Care and maintenance; legal rights preserved | Third-country Strategic Project status; Serbian and EU policy backing | Institutional legitimacy and domestic permitting | Formal restart of permitting under a credible consultation process |
The scorecard is not a ranking of geological quality. It is a map of the risk that must be retired before each project can become financeable and durable.
Greece — Skouries: after the permits, the hard part
Eldorado Gold's Skouries copper-gold project spent the better part of a decade as Europe's emblem of permitting warfare, surviving successive governments, Council of State litigation and a renegotiated investment agreement with the Greek state. As at 31 March 2026, the project was approximately 94% complete. Eldorado expected first copper-gold concentrate in the third quarter of 2026 — a target itself revised from the first quarter — and commercial production in the fourth quarter, against a revised Phase 2 capital estimate of approximately US$1.315 billion.
There are two lessons. The first is familiar: Skouries moved only when political support was converted into enforceable, project-specific certainty — a revised investment framework, not a press release. The second is less comfortable: the last permit is not the finish line. Europe's relatively thin recent pipeline of large greenfield metal-mine developments means that project-specific construction, commissioning and operating depth should not be assumed. Skouries will be judged not on the ribbon-cutting but on the ramp-up.
Finland — Keliber: a mine can be finished and still not be a business
Keliber is the most advanced answer to the question "what does the complete European lithium chain look like?" The project links the Syväjärvi mine, the Päiväneva concentrator and the Kokkola lithium-hydroxide refinery. By early 2026, Sibanye-Stillwater had elected a staged start-up: commission the mine and concentrator while deferring the decision on full refinery ramp-up pending market conditions. Construction and commissioning expenditure was estimated at approximately €783 million.
Keliber has substantially solved permitting, integration, jurisdiction and construction — everything European policy knows how to reward — and remains exposed to the one variable no designation reaches: price. A designation is not a permit; a permit is not a mine; and a mine is not yet a business. If the Union wants counter-cyclical supply security, it will eventually have to confront the demand side — minimum-price offtakes, contracts for difference, strategic purchasing or other price-gap instruments — rather than capital expenditure alone. The EU–US critical-minerals dialogue in 2026, which contemplated exploration of price-support and offtake tools, shows that policymakers have begun to recognise the issue.
Finland — Sakatti: a clear early collision between the CRMA and Natura 2000
Anglo American's Sakatti deposit in Lapland — copper, nickel and platinum-group metals closely aligned with the EU's strategic list — lies beneath the Viiankiaapa mire, a Natura 2000 site. The project has therefore been routed toward the Habitats Directive derogation framework rather than around it. In May 2026, the Regional Council of Lapland approved a phased regional plan — incorporating the request to derogate from Natura 2000 protection — for submission to the Finnish Government, while pre-feasibility and feasibility work is expected to continue before an investment decision.
Sakatti is what it has always been: an environmental-law project containing an exceptional orebody. It may become one of the clearest early tests of whether Article 10(2)'s public-interest presumption can carry a metal mine through Article 6(4)'s surviving requirements — alternatives, compensation and the coherence of Natura 2000 — and through the judicial review likely to follow any derogation decision. Strategic designation in Brussels does not prevent annulment in a national court.
Germany — Lionheart: industrial policy expressed as a capital structure
Vulcan Energy's Lionheart project in the Upper Rhine Valley — lithium from geothermal brine, with renewable heat and power as co-products — reached financial close in May 2026 on a package of approximately €2.2 billion. The stack combined European Investment Bank lending, commercial debt, export-credit support, German federal and state grants, policy-linked and strategic equity, and long-term industrial offtake arrangements. Commercial production is targeted for 2028 at approximately 24,000 tonnes of lithium hydroxide a year.
Lionheart matters because public institutions did not merely put the project on a list; they helped assemble a financing architecture that closed in a weak lithium market. It is the strongest evidence to date that "government-backed" can be made to mean something bankable. The question it cannot yet answer is replicability: Lionheart's technology, energy co-revenues and German setting make it an imperfect template. Blended finance closed one project. A financing system would close ten.
France — EMILI: the state as project co-creator
Imerys' EMILI project at Beauvoir would produce approximately 34,000 tonnes of lithium hydroxide a year from beneath a working kaolin quarry. France has treated it as a matter of state design rather than state endorsement: a 2024 decree declared it a project of major national interest; a formal public debate evolved into continuing supervised consultation; and in February 2026 the French state agreed to take a minority equity interest in the project company, reported at €50 million.
The comparison with Imerys' British Lithium project in Cornwall is instructive but not conclusive. British Lithium was placed on care and maintenance in early 2026 while EMILI continued to advance with state capital and national-priority status. The projects differ in geology, engineering, permitting and economics, but the comparison strongly suggests that direct sovereign participation influenced capital-allocation priority. EMILI's own test remains ahead: the strongest version of the project is one that uses state alignment to meet France's environmental and consultation standards, not to bypass them.
Czech Republic — Cínovec: the institutional advantage, and the honest timetable
Cínovec, on the Czech–German border, is one of Europe's largest undeveloped lithium resources. It is majority-owned through Geomet by ČEZ, the state-controlled utility. A definitive feasibility study completed in December 2025 contemplated approximately US$2.16 billion of capital for annual production of about 37,500 tonnes of battery-grade lithium carbonate over a 26-year life. The environmental assessment process is under way, the study indicated commissioning around 2031, and a mid-2026 optimisation study has identified potential capital savings.
Read that timetable against the policy calendar and the point makes itself: a project in a historic mining district, with significant brownfield characteristics, a state-linked owner and strategic designation in Prague and Brussels still runs from designation to production in roughly six years — if nothing material goes wrong. State participation can align permitting, infrastructure and demand. It is not a permit, and it does not compress geology, engineering or ramp-up. Cínovec's advantage is institutional rather than purely geological; its timetable is an unusually honest statement of what "fast" means in Europe even when much is aligned.
Portugal — Barroso: fast-tracking meets the commons
Savannah Resources' Barroso project — one of Western Europe's largest planned spodumene developments — holds a conditional environmental approval, EU Strategic Project status and a non-reimbursable Portuguese state grant of up to €110 million, part of it contingent on operational performance. It also sits in a landscape recognised by the FAO as a globally important agricultural heritage system, amid communities that have contested the project for years. In June 2026, an injunction obtained by holders of communal land halted fieldwork for three weeks — until the Government, by reasoned resolution declaring the project of national and European interest, removed the injunction's suspensive effect. The court did not reverse its ruling; the Government used a separate statutory mechanism to remove its suspensive effect. A separate challenge to the Commission's Strategic Project designation, filed before the EU General Court in February 2026, illustrates that designation itself can become a reviewable and contested administrative act.
Savannah has prevailed in a series of challenges, and the state has repeatedly supported the project. But a development that must litigate its way onto the land, parcel by parcel, carries a cost that does not appear in the feasibility study and a schedule assumption no lawyer should certify without qualification. A government can shorten its own procedures, but it cannot order a community to extend trust. Procedural acceleration does not resolve a legitimacy contest; it relocates it — to the courtroom, the roadside and ultimately the ballot box. Social licence is core project architecture, to be designed and priced from day one, not an ESG overlay retrofitted between the DFS and the FID.
Serbia — Jadar: the first high-profile third-country Strategic Project casualty
Jadar's chronology is worth reading twice. In June 2025, the Commission designated the project as a Strategic Project outside the EU — a designation covering the mine, not the planned processing plant. In November 2025, Rio Tinto placed it on care and maintenance because of the lack of permitting progress, after opposition to the mine had fused with a broader anti-corruption movement and distrust of public institutions.
Jadar was never simply a mining project with an environmental objection. Once opposition attached to the credibility of the state itself — its courts, regulators and capacity to hold a powerful investor to its commitments — additional technical studies could not answer the question actually being asked. Strategic designation from Brussels risked making that problem worse by confirming, in the eyes of opponents, that the decision had been taken elsewhere. Investment treaties, where available, are compensation mechanisms rather than development mechanisms. Arbitration may recover money; it does not produce lithium.
The quiet successes are brownfield, brownfield-adjacent and redesigned legacy projects
Set the famous names aside and look at what advanced in the past year: a mining lease for a redesigned Norra Kärr project after a decade of permitting; LKAB's Per Geijer rare-earths deposit beneath an operating iron-ore complex in Kiruna; Cínovec in a historic mining district; EMILI beneath a working quarry; and Skouries within an established mining concession. The common thread is not that every project is technically brownfield. It is that each inherits some combination of infrastructure, workforce, geological knowledge, industrial capability and communities more familiar with industrial activity — although familiarity is not consent.
Europe's most productive near-term strategy is therefore likely to include expansions and undergrounds at operating sites, reopened historic districts, by-product recovery, and reprocessing of tailings and waste. A tonne of strategic material recovered from an operating industrial system can be worth more, in time- and risk-adjusted terms, than several tonnes in a greenfield deposit with no executable route to construction. The Commission's project lists increasingly reflect this. Investor portfolios should too.
The missing middle: processing, qualification and customers
Extraction is the photogenic end of the problem. In many commodities, the decisive vulnerability lies downstream. Several Strategic Projects still lack an established European offtake or processing route, and a European mine that remains structurally dependent on Asian processing delivers only part of the supply-security benefit while leaving the decisive bottleneck offshore. The 2025 export-control shock made the point empirically: European industry, rather than European mines, was pushed into crisis procurement.
The milestone that matters is not "first ore." It is qualified, specification-compliant European material delivered into an operating industrial supply chain at a sustainable margin. Counsel drafting offtakes, tolling agreements, streams and royalties should treat processing capacity, qualification timelines, customer acceptance and substitute-processing rights as project dependencies of the same rank as permits — because that is what they now are.
Rank government support by what it actually does
"Government-backed" has become the most overworked phrase in European mining. The 2025–26 record permits a more disciplined taxonomy, in ascending order of practical value: political endorsement; strategic designation and administrative priority; grants and subsidised debt; state guarantees and policy-bank credit; state equity; infrastructure and offtake commitments; and, rarest and most valuable, a fully blended capital stack capable of closing the financing. The Clean Industrial Deal State Aid Framework adopted in June 2025 gives Member States additional room to support strategic industrial capacity, subject to its conditions and the Commission's state-aid disciplines.
State equity can align a sovereign with completion, but it also introduces governance rights, policy objectives, transfer restrictions, local-processing commitments and exit questions. Public support must therefore be analysed by instrument, amount, conditions, duration, state-aid status and enforceability. If it cannot be traced to an operative legal instrument identifying the exposure, responsible public body, milestones and consequences of non-performance, it should not be credited in the financing model. It is encouragement, not bankable support.
Conclusion: the test is institutional, and the deadline is real
Europe has changed the language of mining faster than any jurisdiction in my professional lifetime. Deposits once discussed primarily as environmental liabilities are now discussed as strategic assets; governments that once kept extraction at arm's length now buy equity in it. That transformation is real. It is also insufficient. By early 2026, the 47 EU Strategic Projects included only a small number in construction. In the project sample considered here, the ledger contains one marquee financial close, one physically completed integrated lithium chain awaiting full commercial ramp-up, one imminent copper-gold start-up, a major Natura 2000 test, a state-created French development, a long-dated Czech project, a Portuguese land and legitimacy contest, and a third-country flagship placed on care and maintenance.
The CRMA has done what law can do at the level of designation. What Europe has not yet built is the repeatable institutional process: timely and legally durable permitting decisions; environmental standards that are demanding and decisive; financing that survives the bottom of the price cycle; communities engaged early enough to affect design; and downstream capacity that turns ore into security. Until that process exists, each European mine will remain a bespoke, hard-won exception.
Robert Mason is the founder of Mason Law and advises mining companies, investors and governments on projects and transactions worldwide. This article is general commentary, not legal advice.
Selected sources and notes
The following sources support the principal legal, policy and project-status propositions in this article. They are not intended to be exhaustive. Project status is current to 15 July 2026.
- Regulation (EU) 2024/1252 establishing a framework for ensuring a secure and sustainable supply of critical raw materials, including Articles 5, 10 and 11.
- European Commission, "Selected strategic projects under CRMA"; EU projects approved 25 March 2025 and non-EU projects approved 4 June 2025.
- European Court of Auditors, Special Report 04/2026, "Critical raw materials for the energy transition," published 2 February 2026, especially paragraphs 99–103, Figure 23 and Annex VII (sample of nineteen successful applications; stage data based on applicants' self-declarations).
- European Commission, RESourceEU action plan and related public materials, December 2025, including proposed funding mobilisation, a European raw-materials centre, joint purchasing and coordinated stockpiling.
- Eldorado Gold, Skouries project page and project progress update, updated April 2026.
- Sibanye-Stillwater, "Update on the Keliber lithium project," 19 January 2026, and subsequent Keliber project updates through May 2026.
- Anglo American Finland and Finnish regional planning materials concerning Sakatti, Natura 2000 assessment and the May 2026 regional-plan decision.
- Vulcan Energy Resources, Lionheart Phase One financing and financial-close announcements, May 2026.
- France, Decree No. 2024-740 of 5 July 2024; Imerys announcement concerning the French state's minority investment in EMILI, February 2026; and Imerys portfolio materials concerning British Lithium's care-and-maintenance status.
- European Metals Holdings / Geomet, Cínovec definitive feasibility study, December 2025; environmental-assessment and mid-2026 optimisation updates; and Czech state-aid approval materials concerning support of up to €360 million.
- Savannah Resources, Barroso project, grant and timetable updates; public materials concerning the June 2026 land-access injunction and the Portuguese Government reasoned resolution declaring the project of national and European interest and removing the order's suspensive effect; and the February 2026 challenge to the Strategic Project designation before the EU General Court.
- European Commission, non-EU Strategic Project decision; Rio Tinto, Jadar project updates through 2026.
- Leading Edge Materials, Norra Kärr mining-lease announcement, June 2026; LKAB materials concerning Per Geijer.
- EU–US critical-minerals framework announced in April 2026, including exploration of price-support, offtake and stockpiling tools.
- European Commission, Clean Industrial Deal State Aid Framework, adopted June 2025.
- Public trade and policy announcements concerning China's April 2025 rare-earth and magnet export controls, which remain in force, and the November 2025 temporary suspension into 2026 of the October 2025 expansion measures.